Heading to North Beach? Plan for a longer-term change on East Surfside Boulevard.
The City of Corpus Christi says its $2.1 million reconstruction project began Monday, November 9, 2026. East Surfside Boulevard between Breakwater Avenue and Elm Street, along with a connecting section of Elm Street, will be closed through May 2027.
Access to residential and business properties will remain open, according to the city. Follow posted signs and allow extra time when traveling through the area.
The project includes pavement, drainage, utility, sidewalk, accessibility and lighting improvements. It also converts East Surfside from one-way to two-way traffic between Breakwater Avenue and Coastal Avenue.
Read the City of Corpus Christi’s full project notice and view the map.
Source: City of Corpus Christi, announcement published November 6, 2026. Construction timelines may change; use the city notice for updates.